PROJECT NO
XYP/QTR-HD/FDN/137-2016SCOPE OF WORK
MUD SLURRY APPLICATION BEFORE POURING CONCRETE WITH XYPEX ADMIX IN THE RAFTPRODUCT USED
XYPEX ADMIX C-1000NF & CONCENTRATEXypex Concentrate was used as a Mud Slurry application over the blinding concrete and surrounding wall areas to have an enhanced protection of the concrete as well as a steel reinforcement. Mud Slurry application was initiated 4 hrs prior to Concrete Pouring schedule. Concrete with Xypex Admix C-1000NF was poured in the entire raft as a primary and only waterproofing solution for the project. Enhanced chemical protection and durability of the concrete was the requirement of the client.